RTU Replacement

Challenge Accepted

• Replace 22 electric multizone units with VAV natural gas RTU's


• Coordinate with roof replacement


• Shutdown major intersection each of 6 weekends


• Arrange for new gas piping below 6-lane street


• Install hybrid wireless/wired BAS system with energy monitoring capability


• Install instructional geothermal well


• Replace welding shop and woodworking exhaust fans


• Replace split chiller for cafeteria with air-cooled condensing unit and replace cafeteria make-up air unit

Client
Project Type
Energy Retrofit
Service Sector
Educational Institution
Challenge Met
  • McCauley performed as design-build prime mechanical contractor
  • Zero-incident safety record across all trades
  • Complete turnkey from demo to start-up of 4 units each of 6 weekends
  • Operational portions of the facility minimally impacted during construction
  • Energy reduction and enhanced thermal comfort goals met